1. Site readiness check
Floor level within tolerance, clear height confirmed, columns and sprinklers measured, power points placed. We send a readiness form 30 days before shipping.

Site Readiness · Install Crew · Timeline · Handover
Design and price get most of the attention, but projects are won or lost on site. This guide covers the part that starts when containers arrive: what the building must be ready for, how many installers you need, how long each equipment type takes, and the inspection checklist you sign before opening day.
Design Framework
Each phase has a gate. Moving to the next one before the gate is cleared is the most common cause of delay and re-work.
Floor level within tolerance, clear height confirmed, columns and sprinklers measured, power points placed. We send a readiness form 30 days before shipping.
Containers are cleared with the packing list and certificates. Unloading needs a forklift or pallet jack and a dry staging area close to the hall.
Steel columns, decks and beams go up first, levelled and anchored. This is the phase that needs the most installers.
Padding, nets, slides, trampoline beds, ninja obstacles and themed panels are fitted after the frame passes a torque check.
Use zones, gaps, fixings and surfacing are checked against the design, then staff are trained on daily checks before the keys change hands.
Equipment Mix
Turnkey means one party is responsible from site check to handover. These are the deliverables you should see in writing.
Anchor plans, column positions and section heights issued before production so the site can be prepared.
A lead supervisor from the factory plus local or factory installers, depending on project size and budget.
Shipped with the order so work never waits on a missing anchor bolt or special wrench.
Common padding, net ties, bolts and covers held on site for the first months of operation.
Daily, weekly and monthly inspection routines, with sign-off sheets your team uses from day one.
Certificates, as-built drawings, maintenance manual and warranty registration in one file.



Planning ranges for a trained crew working standard shifts in a ready building.
| Project type | Area | Crew size | Install days | Key site requirement |
|---|---|---|---|---|
| Soft play structure | 100–300 m² | 3–4 | 7–10 | Level floor, 3.5–5 m clear height |
| Multi-level playground | 300–800 m² | 4–6 | 10–18 | Anchor points, ≥ 4.5 m clear height |
| Trampoline park | 500–1,500 m² | 4–6 | 12–20 | Flat slab, foam pit excavation or raised deck |
| Ninja course | 150–400 m² | 3–4 | 6–10 | Overhead load capacity confirmed |
| Full FEC (mixed) | 1,000–3,000 m² | 6–10 | 18–30 | Phased handover by zone |
Ranges assume the site passed the readiness check. Customs delays, unfinished ceilings or late electrics extend the timeline.
Best-Fit Buyers
Turnkey is most valuable when the owner does not have an in-house construction team.
One contract and one point of contact from design to opening day.
Factory supervision on site means the structure is built exactly as engineered.
Fixed install windows that fit around tenant fit-out schedules.
The same crew and checklist across every location keeps quality consistent.
FAQ
Site readiness checks, delivery coordination, a supervised install crew, tools and fixings, staff training, inspection and a full handover file.
Most projects take 7–21 days on site once the building is ready. Large mixed FECs can take 3–4 weeks and are often handed over zone by zone.
Single-level soft play can work at about 3.5 m. Multi-level structures usually need 4.5 m or more, measured below sprinklers, ducts and lights.
Yes. Many projects use a local crew led by a factory supervisor, which reduces travel cost while keeping quality control.
Floor, ceiling, lighting, sprinklers and main electrics. Painting and flooring outside the play area can continue in parallel.
The install supervisor runs the internal checklist; many markets also require an independent inspector against ASTM or EN 1176 before opening.
Yes. We send supervisors or full crews to project sites worldwide and provide remote video guidance for smaller orders.
Safety and compliance claims on this page reference the following primary standards and regulatory publications.
Source data as of September 2026
Fill out the form below and our team will send you a custom design proposal and competitive quote within 24 hours.
Get an instant response from our team via WhatsApp. We're online 12+ hours daily.
🎯 We respond to all inquiries within 24 hours with a free 3D design concept and detailed quote — no commitment required.